DALGARANGA GOLD MINE VILLAGE ACCOMMODATION
June 2017
Gascoyne Resources aquired a second hand C Class waste water plant 50kL/d capacity installed at their new gold mine accommodation site north of Mt Magnet Western Australia to support a 250 man camp
The main issue concerning the client was limited expertise to negotiate regulatory compliance. DoH and local authorities required suitably qualified and experienced people to provide engineering evidence the plant as installed would comply to license conditions.
TMC was engaged to enable the plant to be certified and commissioned to DoH and local government authority compliance together working with contractors to initiate modifications to the facility enabling efficient ongoing operation.
Certification and compliance achieved in the required time frame.